Buffer Report
Project Status Date: 10/15/03 5:00 PM
Project: SA Office Building Plan
Throughput per Month: $25000
| Task ID | Buffer Name | Buffer End Date | Expected Finish | Buffer Length | Buffer Guide | Protection Ratio | Buffer Left | Chain Left | Check Task | Comments |
| 14 | FB protecting Backfill & Rough Grade | 11/14/03 2:20 PM | 10/31/03 2:20 PM | 2 days | 8 days | 5 | 2 days | 4 days | 3 | |
| 18 | FB protecting Plumbing | 11/21/03 2:20 PM | 11/5/03 2:20 PM | 3.61 days | 8.39 days | 3.33 | 3.61 days | 7 days | 3 | |
| 20 | FB protecting Drywall | 12/11/03 2:20 PM | 11/4/03 2:20 PM | 2.83 days | 24.17 days | 9.54 | 2.83 days | 6 days | 3 | |
| 30 | FB protecting Interior Complete | 12/23/03 2:20 PM | 11/11/03 2:20 PM | 4.12 days | 25.88 days | 7.28 | 4.12 days | 11 days | 3 | |
| 32 | FB protecting Interior Complete | 12/23/03 2:20 PM | 12/1/03 2:20 PM | 2 days | 14 days | 8 | 2 days | 2 days | 3 | |
| 39 | FB protecting PAINT TOUCH UP - | 1/8/04 3:39 PM | 12/29/03 2:20 PM | 2 days | 6.16 days | 4.08 | 2 days | 4 days | 3 | |
| 41 | FB protecting PAINT TOUCH UP - | 1/8/04 3:39 PM | 12/31/03 2:20 PM | 2 days | 4.16 days | 3.08 | 2 days | 2 days | 3 | |
| 45 | FB protecting PAINT TOUCH UP - | 1/8/04 3:39 PM | 12/25/03 2:20 PM | 2 days | 8.16 days | 5.08 | 2 days | 2 days | 3 | |
| 47 | FB protecting FINAL INSPECTION - | 1/15/04 3:39 PM | 11/19/03 2:20 PM | 1 day | 40.16 days | 41.16 | 1 day | 1 day | 3 | |
| 49 | BB protecting LOCKSETS AND DOORSTOPS - | 12/31/03 3:39 PM | 12/23/03 2:20 PM | 6.16 days | -0 days | 1 | 6.16 days | 19 days | 3 | |
| 51 | FB protecting PAINT TOUCH UP - | 1/8/04 3:39 PM | 1/6/04 3:39 PM | 2 days | 0 days | 1 | 2 days | 4 days | 50 | |
| 57 | PB protecting End Of Project | 2/12/04 9:02 AM | 1/22/04 3:39 PM | 14.3 days | -0.01 days | 1 | 14.3 days | 65.67 days | 3 |
| Report Date: 10/2/03 12:00 AM |
| Project Manager: Scott Button |