Project Collect Status
Project Status Date: 10/15/03 5:00 PM
| Project Name: SA Office Building Plan |
| Actual Start Date | Expected Start Date | Duration (Days) | Remaining Duration (Days) | Safe Duration (Days) | Actual Finish Date | Task ID | Task Name | Comments |
| 10/16/03 2:20 PM | 2 days | 2 days | 3 days | 4 | Sitework | |||
| 10/20/03 2:20 PM | 5 days | 5 days | 10 days | 5 | Foundation | Concrete Ordered | ||
| 10/27/03 2:20 PM | 4 days | 4 days | 6 days | 7 | Water | |||
| 10/31/03 2:20 PM | 2 days | 2 days | 4 days | 8 | Telephone | 1-800-397-1896 | ||
| 11/4/03 2:20 PM | 3 days | 3 days | 5 days | 9 | Gas | |||
| 10/27/03 2:20 PM | 4 days | 4 days | 6 days | 13 | Structural Steel | |||
| 10/31/03 2:20 PM | 3 days | 3 days | 6 days | 17 | Roofing | Roofing supplies delivered | ||
| 10/31/03 2:20 PM | 2 days | 2 days | 4 days | 19 | Windows & Doors |
| Report Date: 10/2/03 12:00 AM |
| Start Date: 10/15/03 5:00 PM |
| Horizon Days: 14 |
| Project Manager: Scott Button |