Upcoming Tasks by Project
Overallocated resources: (None)
| Project Status Date | 10/15/03 5:00 PM |
| Total # of Tasks | 37 |
| # of Remaining Tasks | 37 |
| # of Remaining Critical Chain Tasks | 27 |
| Buffer Name | Protection Ratio | Expected Finish | Buffered Finish | Remaining Duration |
| PB protecting End Of Project | 1 | 1/22/04 3:39 PM | 2/12/04 9:02 AM | 14.3 days |
| Task Prioritization Metric | Expected Start Date | Remaining Duration (Days) | Task ID | Resource Name | Task Name | Comments |
| 0.24 | 10/15/03 8:00 AM | 1.67 days | 3 | Equipment
Operator |
Excavation | |
| 0.24 | 10/16/03 2:20 PM | 2 days | 4 | Builder |
Sitework | |
| 0.24 | 10/20/03 2:20 PM | 5 days | 5 | Builder |
Foundation | Concrete Ordered |
| 0.24 | 10/27/03 2:20 PM | 4 days | 7 | Plumbers |
Water | |
| 0.24 | 10/31/03 2:20 PM | 2 days | 8 | Electrician |
Telephone | 1-800-397-1896 |
| 0.24 | 11/4/03 2:20 PM | 3 days | 9 | Plumbers |
Gas | |
| 0.24 | 10/27/03 2:20 PM | 4 days | 13 | Builder |
Structural Steel | |
| 1 | 10/31/03 2:20 PM | 3 days | 17 | Builder |
Roofing | Roofing supplies delivered |
| 1 | 10/31/03 2:20 PM | 2 days | 19 | Builder |
Windows & Doors |
| Report Date: 10/2/03 12:00 AM |
| Start Date: 10/15/03 5:00 PM |
| Horizon Days: 14 |
| Project Manager: Scott Button |