Upcoming Tasks by Project


"What should I monitor in SA Office Building Plan?"

Overallocated resources: (None)

Project Status:
Project Status Date 10/15/03 5:00 PM
Total # of Tasks 37
# of Remaining Tasks 37
# of Remaining Critical Chain Tasks 27

Project Buffers:
Buffer Name Protection Ratio Expected Finish Buffered Finish Remaining Duration
PB protecting End Of Project 1 1/22/04 3:39 PM 2/12/04 9:02 AM 14.3 days

Tasks:
Task Prioritization Metric Expected Start Date Remaining Duration (Days) Task ID Resource Name Task Name Comments
0.24 10/15/03 8:00 AM 1.67 days 3 Equipment Operator
Excavation
0.24 10/16/03 2:20 PM 2 days 4 Builder
Sitework
0.24 10/20/03 2:20 PM 5 days 5 Builder
Foundation Concrete Ordered
0.24 10/27/03 2:20 PM 4 days 7 Plumbers
Water
0.24 10/31/03 2:20 PM 2 days 8 Electrician
Telephone 1-800-397-1896
0.24 11/4/03 2:20 PM 3 days 9 Plumbers
Gas
0.24 10/27/03 2:20 PM 4 days 13 Builder
Structural Steel
1 10/31/03 2:20 PM 3 days 17 Builder
Roofing Roofing supplies delivered
1 10/31/03 2:20 PM 2 days 19 Builder
Windows & Doors





Report Date: 10/2/03 12:00 AM
Start Date: 10/15/03 5:00 PM
Horizon Days: 14
Project Manager: Scott Button