Upcoming Tasks by Resource
Project Status Date: 10/15/03 5:00 PM
Resource: Builder
| Resource Name | Task Name | Project Name | Task Prioritization Metric | Expected Start | Remaining Duration (Days) | Task ID | Notes |
| Builder[4] | Sitework | SA Office Building Plan | 0.24 | 10/16/03 2:20 PM | 2 days | 4 | |
| Builder[6] | Foundation | SA Office Building Plan | 0.24 | 10/20/03 2:20 PM | 5 days | 5 | Concrete Ordered |
| Builder[6] | Structural Steel | SA Office Building Plan | 0.24 | 10/27/03 2:20 PM | 4 days | 13 | |
| Builder[3] | Roofing | SA Office Building Plan | 1 | 10/31/03 2:20 PM | 3 days | 17 | Roofing supplies delivered |
| Builder[3] | Windows & Doors | SA Office Building Plan | 1 | 10/31/03 2:20 PM | 2 days | 19 |
Resource: Electrician
| Resource Name | Task Name | Project Name | Task Prioritization Metric | Expected Start | Remaining Duration (Days) | Task ID | Notes |
| Electrician[2] | Telephone | SA Office Building Plan | 0.24 | 10/31/03 2:20 PM | 2 days | 8 | 1-800-397-1896 |
Resource: Plumbers
| Resource Name | Task Name | Project Name | Task Prioritization Metric | Expected Start | Remaining Duration (Days) | Task ID | Notes |
| Plumbers[2] | Water | SA Office Building Plan | 0.24 | 10/27/03 2:20 PM | 4 days | 7 | |
| Plumbers[2] | Gas | SA Office Building Plan | 0.24 | 11/4/03 2:20 PM | 3 days | 9 |
| Report Date: 10/2/03 12:00 AM |
| Start Date: 10/15/03 5:00 PM |
| Horizon Days: 14 |
| Project Manager: Scott Button |