Upcoming Tasks by Resource

Project Status Date: 10/15/03 5:00 PM


"Builder: What task should I complete next?"

Resource: Builder


Resource Name Task Name Project Name Task Prioritization Metric Expected Start Remaining Duration (Days) Task ID Notes
Builder[4] Sitework SA Office Building Plan 0.24 10/16/03 2:20 PM 2 days 4
Builder[6] Foundation SA Office Building Plan 0.24 10/20/03 2:20 PM 5 days 5 Concrete Ordered
Builder[6] Structural Steel SA Office Building Plan 0.24 10/27/03 2:20 PM 4 days 13
Builder[3] Roofing SA Office Building Plan 1 10/31/03 2:20 PM 3 days 17 Roofing supplies delivered
Builder[3] Windows & Doors SA Office Building Plan 1 10/31/03 2:20 PM 2 days 19




"Electrician: What task should I complete next?"

Resource: Electrician


Resource Name Task Name Project Name Task Prioritization Metric Expected Start Remaining Duration (Days) Task ID Notes
Electrician[2] Telephone SA Office Building Plan 0.24 10/31/03 2:20 PM 2 days 8 1-800-397-1896




"Plumbers: What task should I complete next?"

Resource: Plumbers


Resource Name Task Name Project Name Task Prioritization Metric Expected Start Remaining Duration (Days) Task ID Notes
Plumbers[2] Water SA Office Building Plan 0.24 10/27/03 2:20 PM 4 days 7
Plumbers[2] Gas SA Office Building Plan 0.24 11/4/03 2:20 PM 3 days 9




Report Date: 10/2/03 12:00 AM
Start Date: 10/15/03 5:00 PM
Horizon Days: 14
Project Manager: Scott Button
Spherical Angle Home Page