Upcoming Tasks With Predecessors

Project Status Date: 10/15/03 5:00 PM


"Builder: Are any of my inputs for this task being delayed?"

Project Name: SA Office Building Plan
Expected Start Remaining Duration Task ID Task Name Notes
10/16/03 2:20 PM 2 days 4 Sitework

Predecessor details:
Expected Finish Remaining Duration Task ID Task Name Expected Delay
10/16/03 2:20 PM 1.67 days 3 Excavation 0 days



"Electrician: Are any of my inputs for this task being delayed?"

Project Name: SA Office Building Plan
Expected Start Remaining Duration Task ID Task Name Notes
10/31/03 2:20 PM 2 days 8 Telephone 1-800-397-1896

Predecessor details:
Expected Finish Remaining Duration Task ID Task Name Expected Delay
10/31/03 2:20 PM 4 days 7 Water 0 days
10/27/03 2:20 PM 5 days 5 Foundation 0 days
10/20/03 2:20 PM 2 days 4 Sitework 0 days
10/16/03 2:20 PM 1.67 days 3 Excavation 0 days



"Plumbers: Are any of my inputs for this task being delayed?"

Project Name: SA Office Building Plan
Expected Start Remaining Duration Task ID Task Name Notes
10/27/03 2:20 PM 4 days 7 Water

Predecessor details:
Expected Finish Remaining Duration Task ID Task Name Expected Delay
10/27/03 2:20 PM 5 days 5 Foundation 0 days
10/20/03 2:20 PM 2 days 4 Sitework 0 days
10/16/03 2:20 PM 1.67 days 3 Excavation 0 days



Report Date: 10/2/03 12:00 AM
Start Date: 10/15/03 5:00 PM
Horizon Days: 14
Project Manager: Scott Button